
Project Description
This project was constructed in five consecutive phases in order to allow the
owner continued use of the facility throughout construction activities. Allied was
responsible for temporary barricades and public directional signage installation,
relocation, and removal.
Phase I – Construction of temporary wood framed ramp for accessible
Phase II – Construction of new security office entrance and adjacent
interior ramp adjoining the lower lobby to the upper lobby.
Phase III – construction of new interior stair and adjacent ramp.
Phase IV – Construction of new vestibule, new concrete sidewalk, and all
new remaining interior improvements,
Phase V – Consisted of removing all temporary barricades and patch and
repair necessary due to construction activity, restore existing landscaping to original condition
PROJECT MANAGER: Matt Guyot
This email address is being protected from spambots. You need JavaScript enabled to view it.
PROJECT VALUE: $439,000.00
|